Question #11 (Topic: Demo Questions)
A project sponsor requests a one-page summary with key cost risks. The estimator should provide:
Correct Answer: B
Explanation:
Executive dashboards present cost risks clearly for decision-makers.
Question #12 (Topic: Demo Questions)
The estimator includes expected inflation over the project duration. This adjustment is known as:
Correct Answer: B
Explanation: